United Utilities is investing £48 million to upgrade Lancaster Wastewater Treatment Works and improve water quality in Morecambe Bay.
The upgrade will increase stormwater storage at the site and play a key role in enhancing water quality in the nearby River Lune and Morecambe Bay by reducing the number of times that storm overflows operate in heavy rain.
Earlier this year a two-storey welfare compound for onsite workers was installed and early work including vegetation clearance and tank drainage got underway.
By Spring 2029, three ageing storm tanks will have been demolished and replaced with modern, higher-capacity structures. Elements of the existing tanks will be recycled and reused in the construction of new operational sludge tanks, supporting the project’s low-carbon approach.
The additional storage will help increase the amount of storm water the site can store and then return for full treatment. It will play a key role in enhancing water quality in the River Lune and Morecambe Bay by reducing the number of times the storm overflows need to operate during periods of heavy rainfall.
Rob Moore, Wastewater Lead for United Utilities in Lancashire said: “This facility plays a vital role in protecting local rivers and the Morecambe Bay coastline. The upgrade will boost stormwater storage, reduce spills during heavy rainfall, and support cleaner, healthier watercourses.
“The additional storage will act as a ‘holding area’ for the extra rainwater that enters the sewer network during times of heavy rainfall. Holding it back means it isn’t all hitting the wastewater treatment works at the same time and the system is less likely to be overwhelmed.
“We continue to review our network and sites across the county to see where we can make further improvements which help reduce the number of times that storm overflows need to operate.”
The project is being delivered through United Utilities’ new Enterprise delivery model which brings together seven design and construction partners, plus United Utilities, into one integrated team.
Alongside the storm upgrades, a separate project will upgrade the site’s sludge treatment process. This is part of United Utilities’ wider bioresources strategy which is currently on track for completion by spring 2028.


Lancaster-Morecambe train services cancelled amid heavy rain warnings
Pair jailed for violent attack on man in Lancaster street
Panjab Warriors interview: "Morecambe FC will never be in danger while we are owners."
Canal charity gets the ‘hump’ as Lancaster Canal bridges suffer more collision damage
Lancaster wills company donates thousands to help local community groups making a difference
Morecambe Bay Curriculum wins top award
Lancaster film director's latest action movie now showing in UK cinemas
Appeal after Jack Russell dog found collapsed in Lancaster
Lancaster food companies announced as finalists in new Taste Lancashire Producer Awards
New student apartments block opens in Lancaster
Former BBC reporter and ex-Heysham shipping chief launch popular maritime podcast
Lancaster children get life-saving advice at 'Crucial Crew' water safety event
Crews tackle house fire in Heysham
Police appeal after 20 motorbike thefts in 30 days in Lancaster and Morecambe area
Truck driver jailed for causing death of six-year-old Lancaster girl
Former Morecambe Football Club co-chairmen break silence after shock resignation from board
Royal Lancaster Infirmary ward closed to visitors due to norovirus outbreak
Morecambe Football Club stalwarts resign from board
Heysham coffee shop couple take over Morecambe craft ale bar
Morecambe seafront cafe reopens